The Ministry of Electricity said that the loss of about 5,000 megawatts of the national system’s capacity came as a result of the cessation of imported gas supplies, which was reflected in a decrease in supply hours in Baghdad and the governorates, despite the readiness of the stations and the safety of the transmission lines.
The Ministry added that the current electricity production amounts to between 18 and 18.5 thousand megawatts, compared to an actual need of up to 40 thousand megawatts, stressing the continuation of efforts to restore imported gas and develop long-term solutions to address the shortage.
The Ministry revealed four paths to mitigate the effects of the crisis: accelerating maintenance of stations in preparation for the summer, securing alternative fuel in coordination with the Ministry of Oil, conducting load maneuvers, and relying on local gas in some governorates.
She indicated that these measures aim to maintain the stability of electrical equipment during the coming period and reduce any impact on citizens.